Mumbai ยท Residential High-Rise

Skyline Tower โ€” Phase 2

๐Ÿ‘ค Reliance Infra๐Ÿ“… Apr 2024๐Ÿ Mar 2026๐Ÿ’ฐ โ‚น1.2 Cr
78%Progress

Milestones

Foundation & Basement

Completed ยท Jan 2024

Structural Frame (Floors 1โ€“10)

Completed ยท Jul 2024

Structural Frame (Floors 11โ€“24)Active

Target: Sep 2025

MEP & Interiors

Target: Dec 2025

Handover

Target: Mar 2026

Schedule โ€” Gantt

Task
Apr
Jun
Aug
Oct
Dec
Feb
Foundation
Done
Frame Fl. 1โ€“10
Done
Frame Fl. 11โ€“24
Active
MEP Works
Upcoming
Interiors
Upcoming

Active Tasks

TaskAssignedProgressPriorityStatus
Concrete pour โ€” Floor 18 northRamesh K.
60%
HighIn Progress
Rebar installation โ€” Floor 19Suresh P.
35%
MediumIn Progress
Formwork erection โ€” Floor 20Kiran L.
100%
LowDone