Daily Site Reports

Reports โ€” Nov 2024

Wednesday, Nov 20

Skyline Tower โ€” Ph.2 ยท Submitted 6:32 PM by Ramesh Kumar

24
Workers
3
Tasks Done
1
Issues
โ˜€๏ธ
Clear

Work Done Today

Concrete pour for floor 18 north section completed. 120mยณ poured. Rebar work for floor 19 started โ€” 40% complete. Formwork for floor 20 east wing fully erected and inspected.

โš ๏ธ Issues

Formwork misalignment โ€” Floor 18 North Face

3mm deviation. Corrective action taken, re-survey scheduled tomorrow.

๐Ÿ“ธ Site Photos (6)

๐Ÿ—๏ธ
๐Ÿ”ง
๐Ÿงฑ
โš™๏ธ
๐Ÿ“
๐Ÿšง