Reports โ Nov 2024
Wednesday, Nov 20
Skyline Tower โ Ph.2 ยท Submitted 6:32 PM by Ramesh Kumar
24
Workers
3
Tasks Done
1
Issues
โ๏ธ
Clear
Work Done Today
Concrete pour for floor 18 north section completed. 120mยณ poured. Rebar work for floor 19 started โ 40% complete. Formwork for floor 20 east wing fully erected and inspected.
โ ๏ธ Issues
Formwork misalignment โ Floor 18 North Face
3mm deviation. Corrective action taken, re-survey scheduled tomorrow.