Mumbai ยท Residential High-Rise
Skyline Tower โ Phase 2
๐ค Reliance Infra๐
Apr 2024๐ Mar 2026๐ฐ โน1.2 Cr
78%Progress
Milestones
Foundation & Basement
Completed ยท Jan 2024
Structural Frame (Floors 1โ10)
Completed ยท Jul 2024
Structural Frame (Floors 11โ24)Active
Target: Sep 2025
MEP & Interiors
Target: Dec 2025
Handover
Target: Mar 2026
Schedule โ Gantt
Task
Apr
Jun
Aug
Oct
Dec
Feb
Foundation
Done
Frame Fl. 1โ10
Done
Frame Fl. 11โ24
Active
MEP Works
Upcoming
Interiors
Upcoming
Active Tasks
| Task | Assigned | Progress | Priority | Status |
|---|---|---|---|---|
| Concrete pour โ Floor 18 north | Ramesh K. | 60% | High | In Progress |
| Rebar installation โ Floor 19 | Suresh P. | 35% | Medium | In Progress |
| Formwork erection โ Floor 20 | Kiran L. | 100% | Low | Done |